Arbitral Tribunal

Rohan Builders Judgment: A Watershed Moment in Indian Arbitration Law

The Supreme Court’s (“SC”) recent[1]interpretation of the intent and scope of Section 29A of the Arbitration and Conciliation Act, 1996 (“Act” or “Arbitration Act”) has sent ripples through the Indian arbitration landscape. In this landmark verdict, Justices Sanjiv Khanna and R. Mahadevan have provided much-needed clarity and guidance on the extension of time limits for arbitral awards beyond the stipulated timeframe under Section 29A of the Act.Continue Reading Rohan Builders Judgment: A Watershed Moment in Indian Arbitration Law

Novation of Contract and Section 11 Of the Arbitration and Conciliation Act, 1996

The doctrine of severability dictates that the arbitration clause (arbitration agreement) is deemed to be separate or independent from the overarching contract. Therefore, even when a contract’s legality is challenged, the arbitration agreement remains unaffected. However, the novation of a contract, by way of a supplemental/amended agreement, raises an interesting question regarding the validity of the arbitration clause in the original agreement entered into between the parties, which resultantly stands amended or superseded.  The issue about the extent to which the courts can intervene to determine this also requires judicial consideration.Continue Reading Novation of Contract and Section 11 Of the Arbitration and Conciliation Act, 1996

The Evolving Landscape of Pre-Reference Interest in Indian Arbitration Regime

The recent ruling by the Supreme Court of India in Pam Developments Private Limited v. The State of West Bengal & Anr.[1] has reignited discussions on awarding pre-reference interest in arbitration proceedings. The case had arisen from a dispute over delays in a road construction project. Marking a significant development in the evolution of the Indian arbitration law, particularly on granting interest, the Court upheld the arbitrator’s authority to award interest on the awarded sum from the date of the cause of action until the date of the award, even when the contract was silent on the matter. While analysing the Pam Developments case, this blog delves into the nuances of pre-reference interest in light of the existing legal framework and relevant jurisprudence.Continue Reading The Evolving Landscape of Pre-Reference Interest in Indian Arbitration Regime

Can an Arbitral Tribunal’s Mandate be Extended Post Award?

Introduction of Section 29A to the Arbitration and Conciliation Act, 1996 (the “Act”), by way of an amendment in 2015, marked a significant event in the arbitration regime in India. It recognised the sluggishness that had crept into arbitration proceedings and provided for strict timelines for making of an award. The section was further amended in 2019, pursuant to recommendations of Justice B N Srikrishna committee.Continue Reading Can an Arbitral Tribunal’s Mandate be Extended Post Award?

Arbitrability of Disputes: Indian Jurisprudence

[Continued from Part I]

The Vidya Drolia Case: Redefining Arbitrability

In 2019, aiming to solve the conundrum and marking a significant milestone in Indian arbitration, the Supreme Court’s ruling in Vidya Drolia and Ors v. Durga Trading Corporation,[1] (“Vidya Drolia”) laid down the contours of arbitrability. While analysing thearbitrability of Landlord-Tenant disputes governed by the Transfer of Property Act, 1882 (“TPA”), the Supreme Court elucidated that the mere existence of a special statute dealing with certain disputes does not ipso facto render them non-arbitrable, thereby widening the scope of arbitrability and increasing the access to arbitration in complex legal contexts. Continue Reading Arbitrability of Disputes: Indian Jurisprudence (Part 2)

The “modification” conundrum: Sticking to the path of least interference – Part I

Introduction

In matters of arbitration, courts are ordinarily required to adopt a hands-off approach while scrutinizing arbitral awards. This jurisprudence has evolved to a point where minimal interference with awards is seemingly the principle guiding courts in India. Against this backdrop, the Supreme Court (“SC”) is going to consider the question whether the powers under Section 34 of the Arbitration and Conciliation Act, 1996 (the “Act”), extend to the modification of arbitral awards or are limited only to the setting aside of arbitral awards. Central to this question is the role of the courts as envisaged under the Act. Continue Reading The “modification” conundrum: Sticking to the path of least interference – Part I

Big win for PSBs: SC upholds arbitral award awarding damages for breach of substitution agreement, asks state agency to compensate lenders in full

The Hon’ble Supreme Court vide an order dated December 01, 2023, dismissed Special Leave Petition (Civil) No. 19675 of 2023 (“SLP”), filed by Haryana State Industrial and Infrastructure Development Corporation (“HSIIDC”), a state government agency, against concurrent judgments of the Hon’ble Delhi High Court, upholding an arbitral award rendered in favour of a consortium of public sector banks, led by IDBI Bank Limited (“Senior Lenders”). The Ld. arbitral tribunal, comprising Hon’ble Justice (Retd.) R M Lodha, former Chief Justice of India, Hon’ble Justice (Retd.) K S P Radhakrishnan and Hon’ble Justice (Retd.) J Chelameswar (“Ld. Arbitral Tribunal”), finding favour with the case, pleaded on behalf of the Senior Lenders, awarded INR 1737.11 crore (plus additional interest and costs) as damages for HSIIDC’s breach of substitution agreement entered into between the Senior Lenders, HSIIDC and M/s KMP Expressways Limited, i.e. the concessionaire (“KMP”/ “Concessionaire”) (“Arbitral Award”).Continue Reading Big win for PSBs: SC upholds arbitral award awarding damages for breach of substitution agreement, asks state agency to compensate lenders in full

An Analysis of Limitation for Appointment of Arbitrator Under Section 11 of the Arbitration & Conciliation Act, 1996

Introduction

In order to foster quick resolution, efficiency and flexibility are the cornerstones of arbitration. The Arbitration and Conciliation Act, 1996 (“the Act”) [1], provides for strict limitations at most stages of the arbitral process. Naturally, Section 11 with its glaring lack of prescribed limitation at the stage of appointment appears conspicuous and almost at odds with the scheme of the Act.Continue Reading An Analysis of Limitation for Appointment of Arbitrator Under Section 11 of the Arbitration & Conciliation Act, 1996

Extension of Mandate of Arbitral Tribunal under Section 29A(4) of the Arbitration and Conciliation Act, 1996: A Primer for Practitioners

INTRODUCTION

Section 29A of the Arbitration and Conciliation Act, 1996 (“Act”), inserted vide theAmending Act of 2015 (w.e.f. 23.10.2015), was meant to introduce time limit for completion of arbitration proceedings. It prescribed a statutory period of 12 (twelve) months from the date the arbitral tribunal enters upon reference. Thereafter, vide the Amending Act of 2019 (w.e.f. 30.08.2019), the prescribed time limit was modified, and the Act required arbitration proceedings to be completed within 12 (twelve) months from the date of completion of pleadings. Further, sub-section (3) of Section 29A of the Act allows an extension of 6 (six) months by mutual consent of the parties for passing the award. Similarly, sub-section (4) of Section 29A of the Act provides that in the event the award is not passed in terms of Section 29A(1) or within the extended period of Section 29A(3), the parties can make an application to the court for extension of mandate of the arbitral tribunal.Continue Reading Extension of Mandate of Arbitral Tribunal under Section 29A(4) of the Arbitration and Conciliation Act, 1996: A Primer for Practitioners

Extension under Section 29A of Arbitration and Conciliation Act, 1996 not a possibility if application for extension is not made while mandate subsisted

The Hon’ble Calcutta High Court in Rohan Builders (India) Pvt. Ltd v Berger Paints India Limited 2023 SCC OnLine Cal 2645 recently deliberated on the issue of whether Courts can extend an arbitral tribunal’s mandate under Section 29A(4) of the Arbitration and Conciliation Act, 1996 (“the Act”), after the mandate of the arbitral tribunal has been terminated.Continue Reading Extension under Section 29A of Arbitration and Conciliation Act, 1996 not a possibility if application for extension is not made while mandate subsisted