Arbitration Act

Unlocking Arbitration Clauses: Incorporation by reference in digital contracts

Introduction

The question of incorporation of arbitration clauses referred to in another document has been a bone of contention between parties, in view of the absence of statutory guidance under Section 7 of the Arbitration and Conciliation Act, 1996 (“Arbitration Act”). Although the principle of incorporating an arbitration clause, referred to in another document is a well-established principle in arbitral jurisprudence,[1] Section 7(5) only provides that the reference should be “such as to make that arbitration clause part of the contract”. Hence, it has been left to the courts to determine the conditions that need to be satisfied for the same.Continue Reading Unlocking Arbitration Clauses: Incorporation by reference in digital contracts

Rohan Builders Judgment: A Watershed Moment in Indian Arbitration Law

The Supreme Court’s (“SC”) recent[1]interpretation of the intent and scope of Section 29A of the Arbitration and Conciliation Act, 1996 (“Act” or “Arbitration Act”) has sent ripples through the Indian arbitration landscape. In this landmark verdict, Justices Sanjiv Khanna and R. Mahadevan have provided much-needed clarity and guidance on the extension of time limits for arbitral awards beyond the stipulated timeframe under Section 29A of the Act.Continue Reading Rohan Builders Judgment: A Watershed Moment in Indian Arbitration Law

The Evolving Landscape of Pre-Reference Interest in Indian Arbitration Regime

The recent ruling by the Supreme Court of India in Pam Developments Private Limited v. The State of West Bengal & Anr.[1] has reignited discussions on awarding pre-reference interest in arbitration proceedings. The case had arisen from a dispute over delays in a road construction project. Marking a significant development in the evolution of the Indian arbitration law, particularly on granting interest, the Court upheld the arbitrator’s authority to award interest on the awarded sum from the date of the cause of action until the date of the award, even when the contract was silent on the matter. While analysing the Pam Developments case, this blog delves into the nuances of pre-reference interest in light of the existing legal framework and relevant jurisprudence.Continue Reading The Evolving Landscape of Pre-Reference Interest in Indian Arbitration Regime

Can an Arbitral Tribunal’s Mandate be Extended Post Award?

Introduction of Section 29A to the Arbitration and Conciliation Act, 1996 (the “Act”), by way of an amendment in 2015, marked a significant event in the arbitration regime in India. It recognised the sluggishness that had crept into arbitration proceedings and provided for strict timelines for making of an award. The section was further amended in 2019, pursuant to recommendations of Justice B N Srikrishna committee.Continue Reading Can an Arbitral Tribunal’s Mandate be Extended Post Award?

Can damages be awarded based on a guess?

A division bench of the Delhi High Court in Cobra Instalaciones Y Servicios, S.A. & Shyam Indus Power Solution Pvt Ltd. v. Haryana Vidyut Prasaran Nigam Ltd. (“HVPNL”)[1] (“Cobra Case”)upheld the quantification of damages by an arbitrator through “honest guesswork” or a “rough and ready method” since it was difficult to quantify the precise amount of loss suffered by the party.

In this blog, we examine the rough and ready approach under Indian law for quantifying damages.Continue Reading Can damages be awarded based on a guess?

Final Word on Enforceability of Unstamped Arbitration Agreements

“It [law of arbitration] is to be expeditious where the law is slow, cheap where the law is costly, simple where the law is technical, a peacemaker instead of a stirrer-up of strife.”[1]

Are arbitration clauses in unstamped or inadequately stamped agreements enforceable? This is a question that has been under legal scrutiny and has seen conflicting views from various constitutional benches of the Supreme Court for over half a decade.Continue Reading Final Word on Enforceability of Unstamped Arbitration Agreements

Pending Section 37 Appeal under Arbitration Act: Not a Legitimate Ground for Entertaining Belated Claim under IBC

The Hon’ble Supreme Court in the landmark RPS Infrastructure Ltd vs. Mukul Sharma[1] judgement, once again delved into the issue of claims being made beyond the statutorily prescribed timelines in a Corporate Insolvency Resolution Process (“CIRP”). In this case, an appeal under Section 37 of the Arbitration and Conciliation Act, 1996 (“Arbitration Act”), was pending against a Section 34 award and the Appellant submitted a claim for the same subsequent to the committee of creditors (“COC”) approving the resolution plan. Continue Reading Pending Section 37 Appeal under Arbitration Act: Not a Legitimate Ground for Entertaining Belated Claim under IBC

Arbitral clause contemplating ambiguous pre-deposit condition is violative of Article 14: Supreme Court holds in a Section 11(6) application

Introduction

The Hon’ble Supreme Court, vide its recent judgment in Lombardi Engineering Ltd. v. State of Uttarakhand[1] adjudicated inter alia upon whether, when deciding an application under Section 11(6) of Arbitration and Conciliation Act, 1996[2] (“1996 Act”), for appointment of a sole arbitrator, the validity of a pre-deposit condition can be looked into on the anvil of Article 14 of the Constitution of India?Continue Reading Arbitral clause contemplating ambiguous pre-deposit condition is violative of Article 14: Supreme Court holds in a Section 11(6) application

The Bombay High Court was recently called upon to decide an application filed by Anupam Mittal (“Applicant”), the founder of shaadi.com, seeking to restrain Westbridge Ventures II Investment Holdings and other directors of People Interactive (India) Private Limited (“Respondents”) from enforcing an anti-suit injunction granted by the High Court of Singapore. The anti-suit injunction restrained the Applicant from proceeding with his oppression and mismanagement petition before the National Company Law Tribunal (“NCLT”) on the ground that parties had agreed to resolve their disputes via arbitration seated in Singapore and disputes pertaining to oppression and mismanagement were arbitrable under Singapore law.Continue Reading Party Autonomy Restrained? Dissecting Bombay High Court’s Anti-Enforcement Injunction Order in Anupam Mittal v. People Interactive (India) Pvt. Ltd.

Disputes

Introduction

The Government of India (“Government”) had announced a one-time voluntary settlement scheme through the Union Budget 2023-24 to settle contractual disputes involving the Government of India or its undertakings. This voluntary settlement process would also be applicable to disputes that have resulted in arbitral awards or court decrees or court orders upholding arbitral awards (hereinafter collectively referred to as “Award”) under challenge. The scheme is called Vivad se Vishwas II (Contractual Disputes). A draft scheme was published for circulation and was open for public comments till March 8, 2023.Continue Reading Execution meeting spirit of the text will determine success of Vivad se Vishwas II