
Summary: The Supreme Court’s landmark ruling in HCC v. BRPNNL has reset India’s arbitration landscape by emphasising that Section 11 appointments are definitive and not subject to further review, thereby slamming the brakes on procedural sabotage. In a case where three years of hearings were derailed by a belated challenge, the Hon’ble Supreme Court reaffirmed that arbitration agreements must be honoured, defects in appointment mechanisms must be cured without killing the clause, and participation without timely objection amounts to waiver. By insulating advanced arbitrations from endless detours, the judgment restores speed, reliability, and commercial focus to India’s dispute resolution framework, especially vital for the construction sector where delays and escalation claims are endemic.
Arbitration in India often promises speed, autonomy, and finality, but too often, parties try to weaponize procedure to derail the very process they agreed to. Few cases illustrate this tension as sharply as Hindustan Construction Company Ltd. v. Bihar Rajya Pul Nirman Nigam Ltd[1],where a fully functional arbitration — three years in the making and 70+ hearings in an already‑constituted construction arbitration — was abruptly frozen when a party attempted to review a High Court’s Section 11 order. The Supreme Court’s reply was unequivocal — no more detours. Section 11 is a gateway, not a revolving door.
Factual Background
In 2014, Bihar Rajya Pul Nirman Nigam Ltd. (“BRPNNL”) awarded Hindustan Construction Company (“HCC”) a contract to construct a bridge over the River Sone. The contract’s Clause 25 created a multi‑tier mechanism: (i) reference to the Deputy Chief Engineer, (ii) appeal to the Managing Director, and (iii) arbitration by an arbitrator appointed by the Managing Director.
First Arbitration (2019-2021): When disputes first arose, the Hon’ble Patna High Court appointed a sole arbitrator under Section 11 of the Arbitration and Conciliation Act, 1996 (“Act”). The tribunal issued an award in HCC’s favour on December 31, 2021, and BRPNNL accepted and implemented it, affirming the existence and functionality of the arbitration agreement between the same parties under the same clause.
Second Arbitration (2020 onward): Fresh prolongation and cost claims followed. After BRPNNL failed to appoint an arbitrator, the Hon’ble High Court again appointed a sole arbitrator under Section 11. The case ran for over three years, with more than 70 hearings and joint applications for extension under Section 29A — until BRPNNL pivoted to a review petition, challenging the very Section 11 appointment order. The Hon’ble Patna High Court stayed proceedings and, in December 2024, dismissed a fresh Section 11 petition holding no arbitration agreement existed — a clear departure from the parties’ prior conduct and the first arbitration’s history.
Judgment
HCC challenged the Hon’ble High Court’s intervention, bringing the matter to the Hon’ble Supreme Court. The Hon’ble Supreme Court held that:
- Section 11 does not confer any review jurisdiction on the High Court, to revisit its own appointment order. Permitting such reviews would undermine expedition and finality, the very values arbitration seeks to secure under Sections 5 and 11(6A) of the Act.
- Minimal judicial intervention implies that Section 11 is conclusively about the existence of an arbitration agreement, not a platform for cyclical challenges.
- Even if an appointment mechanism (e.g., unilateral appointment by a Managing Director) falls foul of Section 12(5) and the Seventh Schedule, the arbitration agreement is severable and remains enforceable. The court’s task is to cure the appointment defect by naming an eligible arbitrator, not to declare the arbitration clause dead on arrival. This protects party autonomy while ensuring independence and impartiality.
- The parties had already invoked Clause 25, secured a prior Section 11 appointment, and implemented the 2021 award, all of which fortified the existence of the arbitration agreement. BRPNNL’s later attempt to deny that agreement was rejected as inconsistent with its own conduct.
- By jointly seeking Section 29A extensions and participating extensively, the respondent waived procedural objections and could not weaponise review to block an advanced arbitration. The Court stressed that participation without timely objection amounts to waiver.
The Hon’ble Supreme Court set aside the Hon’ble Patna High Court’s order, revived the arbitration, and reaffirmed that an arbitration agreement existed and must be honoured, closing the door on mid‑course review manoeuvres. The ruling cements that Section 11 orders are final at the appointment stage; High Courts cannot recall or review their own orders. This reduces satellite litigation, cuts delays, and restores predictability to the intake of arbitrations. For EPC contractors, developers, and public authorities, the message is commercial — get on with the merits. The Hon’ble Supreme Court has insulated advanced arbitrations from derailment via review petitions, supporting quicker resolution of delays, escalation, and prolongation claims endemic to construction.
Conclusion
HCC v. BRPNNL is more than a procedural ruling, it is a recalibration of India’s arbitration ecosystem. By barring review of Section 11 orders, reaffirming severability, and recognising waiver by conduct, the Hon’ble Supreme Court has insulated arbitration from procedural ambushes. For the arbitration community, counsel, institutions, arbitrators, and in‑house teams, the message is unmistakable:
- Arbitration must move forward, not backward.
- Arbitration agreements must be honoured, not hollowed out.
- And Section 11 is a gateway, not a revolving door.
For India’s busy construction sector, this translates to fewer derailments and more decisions on merits, precisely what a modern, project‑intensive economy needs from its dispute‑resolution framework.
[1] 2025 INSC 1365