After Sunset: Courts on post Rohan Builders

The Supreme Court has resolved the debate on filing for an extension of time period under Section 29A of the Arbitration and Conciliation Act, 1996 (the “Act”), after the period for rendering an arbitral award has expired. This judgment was rendered in Rohan Builders (India) Private Limited v. Berger Paints India Private Limited, SLP (C) No. 23320 of 2023 (“Rohan Builders”) on September 12, 2024. Given that several months have passed since the judgment, this blog takes a bird’s eye view on disputes under Section 29A of the Act and how the courts have dealt with them post Rohan BuildersContinue Reading After Sunset: Courts on post Rohan Builders 

Rohan Builders Judgment: A Watershed Moment in Indian Arbitration Law

The Supreme Court’s (“SC”) recent[1]interpretation of the intent and scope of Section 29A of the Arbitration and Conciliation Act, 1996 (“Act” or “Arbitration Act”) has sent ripples through the Indian arbitration landscape. In this landmark verdict, Justices Sanjiv Khanna and R. Mahadevan have provided much-needed clarity and guidance on the extension of time limits for arbitral awards beyond the stipulated timeframe under Section 29A of the Act.Continue Reading Rohan Builders Judgment: A Watershed Moment in Indian Arbitration Law

Can an Arbitral Tribunal’s Mandate be Extended Post Award?

Introduction of Section 29A to the Arbitration and Conciliation Act, 1996 (the “Act”), by way of an amendment in 2015, marked a significant event in the arbitration regime in India. It recognised the sluggishness that had crept into arbitration proceedings and provided for strict timelines for making of an award. The section was further amended in 2019, pursuant to recommendations of Justice B N Srikrishna committee.Continue Reading Can an Arbitral Tribunal’s Mandate be Extended Post Award?

Extension of Mandate of Arbitral Tribunal under Section 29A(4) of the Arbitration and Conciliation Act, 1996: A Primer for Practitioners

INTRODUCTION

Section 29A of the Arbitration and Conciliation Act, 1996 (“Act”), inserted vide theAmending Act of 2015 (w.e.f. 23.10.2015), was meant to introduce time limit for completion of arbitration proceedings. It prescribed a statutory period of 12 (twelve) months from the date the arbitral tribunal enters upon reference. Thereafter, vide the Amending Act of 2019 (w.e.f. 30.08.2019), the prescribed time limit was modified, and the Act required arbitration proceedings to be completed within 12 (twelve) months from the date of completion of pleadings. Further, sub-section (3) of Section 29A of the Act allows an extension of 6 (six) months by mutual consent of the parties for passing the award. Similarly, sub-section (4) of Section 29A of the Act provides that in the event the award is not passed in terms of Section 29A(1) or within the extended period of Section 29A(3), the parties can make an application to the court for extension of mandate of the arbitral tribunal.Continue Reading Extension of Mandate of Arbitral Tribunal under Section 29A(4) of the Arbitration and Conciliation Act, 1996: A Primer for Practitioners

Extension under Section 29A of Arbitration and Conciliation Act, 1996 not a possibility if application for extension is not made while mandate subsisted

The Hon’ble Calcutta High Court in Rohan Builders (India) Pvt. Ltd v Berger Paints India Limited 2023 SCC OnLine Cal 2645 recently deliberated on the issue of whether Courts can extend an arbitral tribunal’s mandate under Section 29A(4) of the Arbitration and Conciliation Act, 1996 (“the Act”), after the mandate of the arbitral tribunal has been terminated.Continue Reading Extension under Section 29A of Arbitration and Conciliation Act, 1996 not a possibility if application for extension is not made while mandate subsisted